Serra de l'Ebre
Needs attentionCatalonia · Wind · 57 MW installed · 5 technicians · manager Mariano O'Hara
17.1 MW
30 %
294 MWh
96.6 %
9 / 13
5
Wind
8.0 m/s S
Irradiance
0 W/m²
Temperature
13.7 °C
Cloud cover
62 %
Conditions
Partly cloudy
Substation
Ascó SE 400 kV
Voltage
399.8 kV
Frequency
49.972 Hz
Power factor
0.991
Curtailment
8 %
Day-ahead price
58.99 €/MWh
Assets
13 assets on site. Open one for its live 3D view.
Wind turbine
WTG-03
Siemens Gamesa SG 5.0-145 · 6.2 MW
Output
0.50 MW
Today
38.9 MWh
Wind
6.4 m/s
Wind turbine
WTG-04
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
4.85 MW
Today
27.8 MWh
Wind
13.3 m/s
Wind turbine
WTG-05
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.00 MW
Today
13.7 MWh
Wind
5.5 m/s
Wind turbine
WTG-07
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.00 MW
Today
32.9 MWh
Wind
9.5 m/s
Wind turbine
WTG-09
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.11 MW
Today
26.3 MWh
Wind
5.6 m/s
Wind turbine
WTG-10
Siemens Gamesa SG 6.6-170 · 4.2 MW
Output
2.83 MW
Today
18.9 MWh
Wind
11.0 m/s
Inverter skid
INV-01
Sungrow SG3125HV-MV · 4.6 MVA
Output
0.39 MW
Today
29.2 MWh
Availability
99.5 %
Inverter skid
INV-02
SMA Sunny Central 4600 UP · 3.1 MVA
Output
1.54 MW
Today
17.0 MWh
Availability
96.3 %